Red Line tunnel work to disrupt night, weekend service through February

WASHINGTON — Red Line trains will share a single track most nights and weekends through mid February as part of the next round of work aimed at reducing the flow of water into the tunnels, Metro said Friday.

Related Stories

The single-tracking will occur in stretches between the Friendship Heights and Grosvenor-Strahthmore stations beginning Dec. 22. But the disruption will likely reduce service along the entire length of the Red Line.

The work involves boring holes in the tunnels to pump a sealant around the tunnel.

General Manager Paul Wiedefeld said last month that additional service disruptions were coming to the Red Line. So far, the sealant has been applied to 2,000 feet of tunnel near the Bethesda and the Medical Center interlocking.

This work is separate from the emergency Red Line shutdown this weekend between the Silver Spring and Rhode Island Avenue stations, which is aimed at fixing cable problems that posed a crash risk.

Here is the Red Line tunnel work and related single-tracking schedule:

Medical Center to Grosvenor
Weeknights (Monday through Thursday)
9 p.m. through closing Dec. 26 to 28, Jan. 2 to 4 and 8 to 11

Weekends
6 p.m. Friday through closing Sunday Dec. 22 to 24
9 p.m. Friday through 6 p.m. Sunday Dec. 29 to 31

Friendship Heights to Grosvenor
Weeknights (Monday through Thursday)
9 p.m. through closing Jan. 16 to 18 and 22 to 25

Weekends
7 a.m. Saturday through closing Monday Jan. 13 to 15
7 a.m. Saturday through closing Sunday Jan. 20 to 21

Friendship Heights to Medical Center
Weeknights (Monday through Thursday)
9 p.m. through closing nightly Jan. 29 to Feb. 1 and Feb 5 to 8 and 12 to 15

Weekends:
7 a.m. Saturday through closing Sunday Jan. 27 to 28, Feb. 3 to 4 and 10 to 11

National Museum of the American Latino to be housed in historic Smithsonian building

The Smithsonian Institution has decided to put the National Museum of the American Latino into an existing, historic building, rather than constructing a new one. The Smithsonian Board of Regents on Monday designated the Arts and Industries Building, a 145-year-old redbrick Victorian structure located between the Smithsonian Castle and the Hirshhorn Museum, as the permanent site of the National Museum of the American Latino, which Congress authorized in 2020. In 2022, the Smithsonian narrowed its survey for permanent locations for the National Museum of the American Latino and the American Women's History Museum to four locations near the National Mall on land owned by the National Park Service. The Arts and Industries Building, located at 900 Jefferson St. SW, was one of the four sites. New construction on National Park Service land would require congressional approval. However, since the Smithsonian already owns the Arts and Industries Building, the institution can place the National Museum of the American Latino in the existing building without additional legislation.