This is why Amtrak's new Acela rollout is not running on track

The Amtrak Office of Inspector General has released a new report that says Amtrak’s rollout of new Acela trains will likely face future delays and cost increases.

It cites Alstom, the manufacturer contracted by Amtrak to make the new train sets, saying the vendor’s designs have not yet met federal safety requirements. Additionally, the train sets the vendor has produced so far have defects it will need to fix or modify before Amtrak can launch revenue service of new Acela trains.

Alstom is producing 28 new high-speed train sets for Amtrak under the contract. Amtrak has not accepted any of the train sets from the vendor as of August 2023, the report said.

12 of the serial train sets and 22 cafe cars produced so far have defects, according to the report. Some are safety-related, including water drainage issues that cause corrosion.

Other problems are more functional, including a report from the vendor that five windows on trains shattered spontaneously and hydraulic systems leaked. There are also problems with misaligned ceiling panels.

The report credits Amtrak for making recent improvements to management of the new Acela program, but says the program is three years behind schedule and current delays have already resulted in cost increases and delayed revenue.

Given Amtrak’s broader plans to update its national rail network, the report recommends Amtrak enhance its process for capturing and incorporating lessons from the program’s stumbles.

The full report is online.

DC nonprofit marks 15 years of making fresh food a corner store staple

Corner stores aren't usually known for being fresh fruit and vegetable hubs. D.C. Central Kitchen has spent 15 years working to change that in the District, with a focus on lower-income neighborhoods without easy access to the healthy choices found in other parts of D.C. Related stories Neighbors fundraise to reopen historic grocery store on Capitol Hill DC Italian grocery and deli crosses the century mark